Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

2x+4y=10 and 3x+7=y by substitution method
Can somebody help me
HELLLPPPPP!!!!!!!!!!!!!!!!!!
These prisms are similar. Find the surface area of the larger prism. Round to the nearest tenth. 5 in. Surface Area = 572 m2 Surface Area = [ ? ] m2 6 in.
d. Application software are developed by software companies ​
Why does Walt Whitman use the word singing in the title "I Hear America Singing"?
Rewrite this measurement with a simpler unit, if possible. 4.5·m2m2m
A rectangular tank measures 60cm by 50cm by 40cm. Water flows into the tank at a rate of 8 litres per minute. At this rate, how long will it take to fill the ta
QI the father 13. A father and mother claim they have been given the wrong baby at the hospital. Both parents are blood type A. The baby they have been given is
Will Mark Brainlest Help Please Please .​