If 24 electricians can wire some new houses in 15 days, how many electricians would be required to do the job in 12 days?.

Respuesta :

shishirshrestha989
shishirshrestha989 shishirshrestha989
  • 04-01-2022

Answer:

here,

electrician/days

24 - 15

x(let). -12

direct proportion,

then,

exchange X up 24 down

or,24*15=12*X

or,24*15divided by 12=X

X=30

hence,30 electrician required to do complete in 12 days

Answer Link

Otras preguntas

To protect Liberty. what did Montesquieu propose? A-People entrust their rights to a strong monarch B-The government be divided into separate branches C- Proper
how can you represent the set of a whole numbers integers and rational numbers are related to each other
Which of the following business ownership structures offers the best quality liability protection but higher taxes? (Select the best answer.) A. Partnership B.
d determine whether the given value is a solution of the open sentence p+2q<16;p=5,q=5
what is 12.375 in expanded form
how do you graph the function f(x-2)+2
which of the following are needed to determine how long an object is in projectile motion? tell me all that apply. a. the initial velocity of the object b. the
Diagram F in Figure 3-1 is an example of ____. a. diffusion c. osmosis b. active transport d. equilibrium
what's the English definition of these?
Which four ethical norms are often used by companies to help individuals make ethical decisions? A. Responsibility to environment, customer, employee, investors